About this Project
The Moray FLOW-Park has been undergoing technical evaluation, environmental planning, extensive stakeholder consultations and site investigation activities and is close to finalising an initial development plan that is both fit-for-purpose and minimises the potential impact on other users of the sea and the wider environment. These efforts are illustrated by the completion of a comprehensive and wide-ranging Scoping Report as part of a full Environmental Impact Assessment programme of activities that goes beyond the minimum statutory requirements and reflects the unique first-of-a kind nature of the Moray FLOW-Park.
Project Pulse
At a Glance
Full Project Lifecycle
Tracking all four stages from initial assessment through to operations.
Document Library
Plain-English overview of the Moray FLOW-Park project.
Supplementary information to the main community factsheet.
Final Screening Opinion from Marine Directorate Scotland confirming that a full Environmental Impact Assessment is required.
Appendix to the Final Screening Opinion (SCR-0121). Redacted in accordance with Marine Directorate Scotland guidance.
EIA Screening Report (SCR-0121) prepared by OSG/GoBe Consultants, submitted to the Marine Directorate, February 2026
Environmental Impact Assessment Scoping (SCOP-0076), prepared by OSG/GoBe Consultants, submitted to the Marine Directorate, August 2026
Habitats Regulations Appraisal Screening Opinion, prepared by OSG/GoBe Consultants, submitted to the Marine Directorate, August 2026
Scoping Opinion from Marine Directorate Scotland setting out what the Environmental Impact Assessment must cover. Includes the response to the HRA Screening Report.
No documents match your current filter.
Public Consultation
This is the first stage of public consultation on the Moray FLOW-Park. We welcome your comments and questions on the proposals.
There are two ways to take part. Anyone can leave a general comment of up to 250 words using the form below. Organisations that would like to send a longer, more detailed response can ask for access to a separate organisation form.
Please note that we are not able to reply to individual comments at this stage. Every comment will be read and considered, and answers to common questions will be published on this page.
Responding as an organisation?
Organisations can ask for access to a longer response form with no word limit.
Tell us who you are and we will review the request. If it is approved you will be sent a link and a password by email.
Questions and answers
Questions raised during the consultation, published with the answer. Nothing here identifies who asked.
Installation operations for FLOW projects are extremely weather dependent, which means that only limited weather windows are available to install the FLOW units during winter months. Installation campaigns are therefore planned to be conducted in summer months, with most commercial scale wind farms planning the campaign over two to three summer seasons. To meet this schedule there needs to be a constant availability of foundations ready and waiting to have the tower and wind turbine generator installed (also known as integration) prior to commissioning and towing offshore. Large numbers of foundations takes up space that exceeds port and harbour capacity, and wet storage is used to avoid blocking the ports, harbours, or manufacturing facilities. The need for Wet Storage has been defined as a critical requirement by industry research projects and published papers.
- Frazer-Nash and the Carbon Trust -Wet Storage Solutions Project for FLWJIP, published Mar 2026
- Renewables UK - Floating Offshore Wind Taskforce: Industry Roadmap 2040
Currently there are no commercial scale FLOW Wet Storage facilities licensed or consented in Scotland, either within or out with existing Harbour Area Authorities.
All new Wet storage facilities require a new or additional seabed lease to be agreed with Crown Estate Scotland and require a Marine License from the Marine Directorate. A full Environmental Impact Assessment and Habitat Regulations Appraisal (if applicable) are required to apply for a Marine License for wet storage.
Moray FLOW-Park® is currently the only Wet Storage facility that has started the consenting and licensing process1, a complex and detailed process that can take 5+ years from starting. No other ports or harbours have yet started the process1.
It is unlikely that a Wet Storage facility that has not already started the consenting and licensing process would be ready and available to meet Scotland’s FLOW project delivery ambitions and the required timelines of already licensed wind farms under development.
¹ Based on publicly submitted documents to Scottish Government licensing bodies
There are very limited ports/facilities in Scotland that have the space or weight bearing capabilities to provide sufficient dry storage for commercial scale floating projects, without significantly impacting the existing ports operations. Dry storage is an option where the FLOW platforms are manufactured at the same location, however where the units are delivered from other ports this adds significant cost, complexity and risk to the project.
In practice Dry Storage along with Wet Storage will form part of the solution to be able to deliver FLOW project ambitions in Scotland, and to help maximise the Scottish and UK local content. All FLOW-Park® logistic modelling accounts for an element of dry storage within the model.
OSG together with ports, developers, and Crown Estate Scotland conducted an extensive search of the Scottish coastline that involved the detailed assessment of technical and consenting requirements to find a suitable location. The two Moray FLOW-Park® areas were agreed between all parties as potential locations that should be prioritised for development of a FLOW-Park®. The area within the Moray Firth is extensively used for anchoring by large commercial marine vessels. This assessment was based on the comparison of technical, consenting and logistics requirements, a key driver being the proximity to ports with plans to support FLOW and to the offshore wind farm locations.
The required EIA report will further define and detail the technical reason for selecting the Moray Firth over alternative locations.
The vast majority of Scotland’s nearshore coastline is located within an environmentally designated area, immediately adjacent to one, or similarly within or adjacent to a National Scenic Area.
Out of the potential 24 FLOW-Park® locations previously identified for detailed technical and commercial assessment only five were not within a designated area.
Three of these sites were deemed unsuitable after further detailed metocean assessment and the remaining two were deemed out with the area of interest for developers for conflicting commercial reasons. Seven of the potential sites were either within or immediately beside National Scenic Areas (NSA).
Unfortunately, it is therefore impossible to avoid locating a technically viable FLOW-Park® in any nearshore location that would not have a level of impact on a designated area. The level of impact will be assessed fully as part of the Environmental Impact Assessment (EIA) process. This need for an EIA also applies to potential alternative locations highlighted in existing press articles.
Scotland’s FLOW project development timeline is constantly changing with projects now significantly delayed from the predicted installation dates at the time ScotWind and INTOG licenses were awarded.
The initial FLOW-Park® requirement for 2 sites with a maximum of 100 parking slots was assessed previously as the maximum requirement, based on expected install dates at the time ScotWind and INTOG licenses were awarded.
Over the following 3 years, further site technical assessment (e.g. Geophysical Survey, Metocean modelling & validation), technical and stakeholder consultation was undertaken to further refine the details and required scale of the Moray FLOW-Park®. This was conducted to ensure that only what was critically needed was included within the consenting envelope. Wind farm developers were included in this engagement to input their required operation timelines and resulted in downsizing of the FLOW-Park® scale and focus on a single area.
The consenting proposal was therefore reduced to 30 mooring slots for foundations and only at a single site. This reduced scale meets the critical industry need for wet storage whilst minimising the potential impacts of the FLOW-Park®.
There are further site investigations/surveys required before the final siting and layout of the FLOW moorings within the FLOW-Park® can be finalised. Retaining the full area within the EIA allows operational flexibility of placement of the moorings to take account of the further data collected. The EIA is based on 30 slots, therefore if successful with the EIA and Marine License that would be the limit set by the Marine Directorate. Any future change to increase this number would require a full revisit of the EIA process and a new Marine License application. Considerable logistical and technical assessments have combined with extensive industry and stakeholder interaction to ‘right-size’ the Moray FLOW-Park®. Work continues to refine the layout and operational plans within this location.
OSG contracted a Metocean specialist company to develop a bespoke weather model for the Moray FLOW-Park® locations, along with two further potential sites. This was the first stage detailed assessment, used to further prioritise and refine the potential FLOW-Park® locations.
The metocean model was validated against existing weather measurement data provided by local Wavebuoys, and existing offshore windfarms. This meets accepted standards from classification societies for wave, wind, and tidal modelling.
For further validation of the Metocean model (as required by classification societies) a Metocean measuring buoy would be installed on site specific to the location prior to commencement of detailed design2.
The analysis indicated an operational uptime of greater than 90% for the Moray FLOW-Park® based on the offshore operational activity weather limits, additionally the validated data provided site specific extreme wave and wind data that enabled concept mooring design to be conducted that meets class society and insurance requirements. This confirmed that the location is sufficiently sheltered and technically suitable to operate as a FLOW-Park® wet storage facility.
2 Subject to successful completion of EIA and Marine License application.
OSG are consulting directly with the relevant fishing industry bodies and directly with active local fishermen who fish in the area through their Fishing Liaison Officer, (for both fixed gear and mobile fishing), to limit the impact on current fishing activities.
The current FLOW-Park® layout has been modified to account for input from the fishing community3.
The EIA process will define the extent of any impact which will be reported.
3 The layout will be liable to change again as further survey work is completed
The extensive and legally required Environmental Impact Assessment and Habitat Regulations Appraisal activities will investigate the potential impacts on all Marine Wildlife as part of the licensing process. This process will define the level of impact expected, which is then for the licensing bodies and consultees to review and comment on. The Moray Firth is one of the most studied areas in the world for Marine Mammals, particularly with regards to interaction with windfarms, offshore vessels and moorings. There is a wealth of information available that will be used to inform the EIA and HRA process, the proposed data sources are referenced in the Scoping Opinion report which is available on both the OSG and the Marine Directorates websites.
OSG were fully aware of the charted seabed obstructions and potential for uncharted obstructions when the FLOW-Park® sites were selected. Specific to the Moray sites, OSG were aware of the Valentine Tanks, and potential for war time aircraft remains and unexploded ordnance. Whilst at least one fatality is connected to the sinking of the tanks, the Commonwealth War Graves Commission does not record which tank is a potential war grave. Considering this uncertainty, all the tanks have been treated with due respect and protected from development.
OSG therefore conducted a high specification seabed survey of the Moray FLOW-Park® including Multi-beam Echo Sounder, Side Scan Sonar and Magnetometer survey, to identify and characterise any seabed (or sub surface) objects.
The survey identified the exact locations of several seabed items including two of the known Valentine tanks within the project boundary. These areas will be classed as 'no infrastructure zones’ where there will be no FLOW units moored or seabed anchors located within their immediate proximity. This protects and respects the integrity of the Valentine Tanks.
OSG are working with the Commonwealth War Graves Commission, Historic Environment Scotland, and UK Hydrographic Office to ensure that the correct co-ordinates of the tanks and any other significant seabed hazards are recorded correctly for the benefit of all sea users and to aid the long-term protection and due respect for these underwater assets.
How we use your information
Offshore Solutions Group Ltd, 4th Floor, 205 Regent Street, London W1B 4HB, is responsible for the information you give us through this consultation.
What we collect
If you leave a comment, we collect your name, email address and comment. If you ask for organisation access or send an organisation response, we also collect your organisation's name and what you tell us about it. To limit repeated submissions, we keep a one-way coded version of your internet address, never the address itself.
Why we collect it
To make sure each person responds once, to consider your views as part of the consultation, and to reply to organisations about access. We will not use your details for marketing, and we will not sell or share them. Our website provider stores the information on our behalf.
Will my comment be published?
Your comment may be included in a consultation report, without your name or contact details. The report will be published as part of the Environmental Impact Assessment Report submitted with the marine licence application. If you respond on behalf of an organisation, the organisation's name may be listed in the report. Where a question is raised, we may also publish it with our answer on this page, with nothing that identifies who asked.
How long we keep it
Names, email addresses and coded internet addresses are deleted when the consultation closes. Comments are kept with no personal details attached.
Our legal basis
We rely on our legitimate interest in consulting the public about the project.